Experimental Study on Force Bearing of Long Span Wide Steel Box Girder Cable-Stayed Bridge in Construction Stage

  In the design and construction of long-span steel box girder cable-stayed bridges,shear lag is often an important factor affecting the stress of bridge structures.A certain waterway super large bridge is a wide-section steel box girder cable-stayed bridge,which adopts cantilever assembly construction to study the influence law of the current section and the current section working condition on the shear lag effect of the completed beam section tested.The results show that The stress is constantly changing as the construction phase changes.On the whole,the stresses at different positions of each section are increasing.From 11:00 to 15:00,the stresses at each measuring point of the beam increase,including the compressive stress at the top of the beam and the tensile stress at the bottom of the beam.

Deyuan Deng Jianxin Lu Zhou Chen Xiaoqing Zhang Guofei Yang

China Construction Steel Structure Corp.Led,Guangzhou,China Foshan University,School of Transportation and Civil Engineering & Architecture,Foshan,China

国际会议

The 2nd International Symposium on Application of Materials Science and Energy Materials (SAMSE 2018) 第二届材料科学应用与能源材料国际研讨会2018年

上海

英文

1-5

2018-12-17(万方平台首次上网日期,不代表论文的发表时间)