SETTLEMENT OF COMPOSITE FOUNDATION - A CASE HISTORY WITH REINFORCEMENT OF STEEL PIPE MICRO-PILE

  This paper presents a case history of high-rise building that is located in deep alluvium deposits with composite foundation.When the building construction approached completion,the monitoring data showed that the foundation settlement and the latest settlement rate was approaching or far more exceeding the control values.Foundation re-analysis demonstrated that even though the foundation capacities could satisfy the design requirement,the total final settlement would be more than 200mm due to the thick compressible soils,which couldnt meet the designed settlement requirement.To guarantee the building security,steel pipe micro-pile as settlement reducer was utilized for its clean construction environment to control post-settlement.The total 624 micro-pile of 18 meter long and 30mm in diameter had been pressed tipping into fine sand layer within 50 days.During and after micro-pile construction,settlement monitoring was carried out by the settlement remarks installed at the columns.The monitoring data demonstrated that during the reinforcement construction the building steadily settled down due to construction disturbance and the differential settlement almost could be negligible.Six months later the settlement tended to convergence and the settlement rate had satisfied the relevant code standard.The method of foundation reinforcement is feasible and successful.

Composite foundation,foundation settlement,steel pipe micro-pile foundation reinforcement monitoring data

Jianping Sun Junhua Xiao Qingpeng Wang

School of Civil Engineering,Shandong Jianzhu University,Jinan,China Institute of Project Appraisal and Reinforcement of Shandong Jianzhu University,Jinan,China

国际会议

2016 International Symposium on Civil and Environmental Engineering(2016年土木与环境工程国际研讨会)

武汉

英文

157-161

2016-12-20(万方平台首次上网日期,不代表论文的发表时间)