Analysis of Baoping Concrete Face Rockfill Dam Infiltrating Status in Early Storage Period
The article focuses on Baoping Hydroelectric Power Station in the early storage phase of seepage for analysis.Seepage monitoring data shows that the overall seepage of the plate dam is small, and anti-seepage curtain and cover of damhassignificant effect.Most slab monitoring parts have stable pressure, but a few have abnormal piezometer measurements.Analysis shows that negligible leakage of the slabexists, and insufficient permeability exists in some cushion parts.In addition, as weirs far has not been put into use, which leads to lack of basic information in deformation of joints and cracks in the slab.It is suggested that it should be put into use soon.
CFRD safety monitoring seepage analysis safety assessment
Zeng Xingying Lu Zhengchao
China Institute of WaterResources and Hydropower Research,Structural Materials Institute, Beijing, 100038, China