Analysis of Box Transformer Oil Chromatographic Abnormal Data in a 35kV Wind Farm

  The design structure of the high voltage winding of the box transformer lead to high voltage between the high voltage winding layers,and electric field of each layer winding end is over-concentration,and the additional loss of load loss is too high,and thus lead to further the enameled wire of high voltage terminal happens partial discharge seriously and cryogenic overheating are discussed through the defects analysis of box transformer and a series of related experiments,hanging core inspection and analysis.If the hydrogen content is overweight seriously,total hydrocarbons is overweight,and methane gas content of total hydrocarbons is very high,ethylene and acetylene is very low,it can initially determine that low-energy partial discharge fault is inside the device are demonstrated.Finally,the corrective measures for the common problem of this group box transformer are presented.

partial discharge oil chromatography total hydrocarbons hydrogen additional loss electric field strength

Wang Qinghao Chen Gang Pang Yanjun Zhang Wenguang Liu Guobin Meng Yu Zhao Cuanzong

Fushun Power Supply Company, Liaoning Electric Power Company Limited, China

国际会议

2012 International Conference on Engineering Materials,Geotechnical Engineering and Environmental Engineering(EMGEEE2012)(2012工程材料、岩石工程和环境工程国际会议)

石家庄

英文

395-398

2012-10-26(万方平台首次上网日期,不代表论文的发表时间)