Blasting Demolition Technology and Vibration Testing of 210m Reinforced Concrete Chimney

  This paper describes the successful experience of the directional control blasting of 210m-high reinforced concrete chimney of Nanchang Power Plant in Jiangxi Province called as First height in Asia.It emphatically describes the pretreatment measures, blasting cut shape and size, blasting parameters, electronic digital detonator detonating network and blasting safety technology.And the blasting vibration was tested and analyzed, and this paper presents the method for opening the arch overlarge oriented window and comprehensive protection method for anti-flyrock splash, vibration reduction and dustfall.Especially, the electronic digital detonator was first applied in the blasting demolition of 210m-high structures, it improves the delay precision and also has a good anti-stray current effect to ensure that the blasting can be safely implemented in the power plant, and it has a good application prospect in the future large-scale and high level complex engineering blasting.

Chimney Directional blasting Electronic digital detonator Overlarge oriented window comprehensive protection

Shunxiang XU Dezhi CHEN

Wuhan University of Science and Technology,Wuhan 430081,China;Wuhan University of Technology,Wuhan,4 Wuhan Safety and Environment Protection Research Institute,Wuhan 430081,China;Wuhan University of Te

国际会议

the 2012 International Conference on Vibration, Structural Engineering and Measurement (2012年振动、结构工程与测量国际会议(ICVSEM2012))

上海

英文

986-990