Field in-situ observation on road-embankment integrating soft soil roadbed

  In the engineering background of a new road-embankment integrating Binjiang Avenue in a city adjacent The Yangtze River,soft soil Roadbed is treated by drainage consolidation method.In-situ observation on test section,which including settlement plate to monitor vertical settlement and inclinometer tube to monitor horizontal settlement,shows that monitoring warning line determined by design is reasonable,and h has certain safety margin.Filling rate has great influence on settlement and lateral displacement rate,and lateral displacement is mainly appeared in mucky clay layer.There exists certain settlement and lateral displacement difference between old embankment and new Roadbed,which would not influence flood control function of embankment.Then monitoring method keeping construction of new Roadbed safe is put forward.

plastic drainage slab road-embankment integrating soft soil roadbed in-situ observation

Yulin ZOU Zhichao DONG Chuan HE Chaofan YAO

MOE Key Laboratory of Transportation Tunnel Engineering,Southwest Jiaotong University,Chengdu,610031 Changjiang Institute of Survey,Planning,Design and Research,Wuhan 430010,China

国际会议

the 2nd International Conference on Electronic & Mechanical Engineering and Information Technology (EMEIT-2012)(2012年电机工程与信息技术国际会议)

沈阳

英文

835-838