An Integrated Scheduling Approach for Flexible JSP

  A colored Petri net is used to model the job shop scheduling problem with dual-resource constraints.The objective of scheduling problems is to minimize make-span.Firstly,the Petri net model of the flexible JSP is constructed based on object-oriented approach.Secondly,GA is applied based on the colored Petri net model.Finally,one example is applied to test the effectiveness of the method.

Petri net object-oriented modeling job shop scheduling problem(JSP)

Tao Ze Wan Runbei

School of Mechanical Engineering,Shenyang Ligong University,Shenyang 110159,China University of Southern California,Los Angeles,90007,USA

国际会议

the 2nd International Conference on Electronic & Mechanical Engineering and Information Technology (EMEIT-2012)(2012年电机工程与信息技术国际会议)

沈阳

英文

1225-1228

2012-09-26(万方平台首次上网日期,不代表论文的发表时间)