Application of Pre-grouting Technique in Yellow River Crossing Tunnel in Eastern Route of South to North Water Transfer Project

  The yellow river crossing tunnel runs through limestone at a depth of about 70m below the level of yellow river.Since the river water,phreatic pore water in loose Quaternary deposits and karst/fissure water in limestone communicates with each other,pre-grouting technique has to be employed before drilling and blasting excavation of the tunnel.

Tunnel Pre-grouting Permeability rate Watertight curtain

Xiaoyan Wang Shiwei Duan Xiane Xu Haoliang Wang

No.60 Dongting Road, Hexi District, Tianjin, China, Postcode 300222 No.83 Yongyangxi Road, Wuqing District, Tianjin, China, Postcode 301700