会议专题

Factors Affecting Productivity of Horizontal Directional Drilling

  Horizontal Directional Drilling (HDD) is a suitable construction method for crossing beneath obstacles,such as rivers and lakes,highways,or special areas such as airport runways.In particular,HDD is the most appropriate,cost effective method for constructing new water and wastewater pipelines where excavation is not practical or possible.HDD operations are capable of traversing various soil conditions and meeting a wide variety of project requirements (pipe size and material,placement distance and depth).Nonetheless,the specific soil conditions and project details are important factors in determining the productivity of the overall operation,and these conditions must therefore be carefully investigated during the HDD design phase.The present case study provides observed HDD productivity values (ft/hr) in different soil formations (shaly clay,sandy shale,and silty clay) based on operations at a single HDD site,serving as a pilot project.In particular,the variation in HDD productivity during the reaming stage is provided based on the soil and project conditions encountered (diameter),while other conditions (e.g.,contractor and HDD machine) remain constant.

Mohmd Sarireh Mohammad Najafi Lawrence Slavin

Full-time Lecturer, Tafila Technical University, Department of Civil Engineering, P.O.Box 179, Tafil Director of the Center for Underground Infrastructure Research and Education(CUIRE), The University Principal, Outside Plant Consulting Services, Inc., 15 Lenape Avenue, Rockaway, NJ, 07866

国际会议

第四十届国际海事委员会会议

北京

英文

1848-1858

2012-10-14(万方平台首次上网日期,不代表论文的发表时间)