Numerical displacement simulation for pit excavating process of diaphragm wall using ADINA

In light of the diaphragm wall excavation process for foundation anchorage of Runyang Bridge, 3-D FEM model based on ADINA software was established to simulate the continuous excavation of the diaphragm wall. The horizontal displacement of the diaphragm wall during the excavation process was simulated^and compared with the monitoring results. Besides, the influencing factors were also analyzed. The results showed that the ADINA software and the 3-D FEM model could simulate the pit excavating process and its displacement accurately.

3-D FEM diaphragm wall displacement

Ren Lifang Lv Jianhong

Shijiazhuang Railway Institute of Technology,Shijiazhuang 050041College of Earth Science and Enginee College of Earth Science and Engineering,HohaiUniversity,Nanjing 201198, China