Research on Utilization Ratio of Grid-Connected Distributed Solar Photovoltaic Sources

To effectively accept the grid-connected distributed solar photovoltaic (PV) output,PV utilization ratio is researched based on the system minimum load at various PV penetrations. The impacts of PV on the electric power system and the main constraints for PV connected to the grid are analyzed. The methods to calculate PV utilization ratio,PV generation cost and annual utilization hours are proposed. The acceptable capacity and utilization of PV can be evaluated by these parameters. Finally,constructive suggestions for optimizing the scheme of PV installation and improving the acceptable capacity of PV are provided.

solar photovoltaic optimization scheme of PV penetration distributed generation

Xiaohui Ge Weiwei Xu Bowen Hong Bo Zhao Hangwei Tong

Zhejiang Electric Power Test and Research Institute,Hangzhou,China,310014

国际会议

2010年中国国际供电会议(CICED 2010)

南京

英文

1292-1297