会议专题

Buckling Analysis with Guyed Tower of 500kv Transmission Line

With guyed Tower(type:LM21) of 500kV transmission lines, the joint bar of tower body and stayguy had been deformed severely in the process of operation. We did the buckling analysis in different load condition with application of finite element method. The results revealed that the nether cross arm yielded under load of cladding ice and imbalance tension. Then we do experiment with prototype tower and acquire corresponding datum. By contrasting the theory results and experimental datum, we can make sure that this method of analsing tower is exact and proper. Finally, we setted out improvemental means that to change material specification of the nether cross arm from 80mmx80mmx6mm to 120mmxl00mmxl4mm. By this insteading, the intensity and deformation of tower have met designing requirements.

SOOkV transmission line guyed tower buckling analysis prototype experiment

Wei Kong Jian Dang

College of Civil Engineering Northeast Dianli University Jilin, China

国际会议

The 2010 International Conference on Computer Application and System Modeling(2010计算机应用与系统建模国际会议 ICCASM 2010)

太原

英文

376-378

2010-10-22(万方平台首次上网日期,不代表论文的发表时间)