An Artificial Bee Colony with Random Key for Resource-Constrained Project Scheduling
This paper proposes an artificial bee colony (ABC for short) algorithm with random key for resourceconstrained project scheduling (RCPSP for short) in real time. Aim at resource saving by the activities, the RCPSP problem attempts to obtain a feasible schedule minimizing the makespan. We modified the artificial bee colony algorithm (named by ABC-RK) for this problem, where the problem representation was based on random key, and a heuristic priority rule to assign activities was also employed. The preliminary experimental results showed the effectiveness of the ABC-RK algorithm.
resource saving artificial bee colony project scheduling random key
Yan-jun Shi Fu-Zhen Qu Wang Chen Bo Li
School of Mechanical Engineering,Dalian University of Technology, Dalian, P.R.China 116024 School of Mechanical Engineering,China North Vehicle Research Institute Beijing, P.R.China 100072