RESEARCH ON RAW MATERIALS REQUIREMENT METHOD WITH COOLING TIME OF COLD ROLLING PRODUCTION
The raw materials requirement problem of cold rolling production system in which relate to complicated structure and various materials flow types. Planner must deal with cooling time of hot mill slabs and rigid operation regulations such as storages have capability limitations and facilities must be run continuously. A mathematical model is built, and an extended two-stage algorithm (ETsA) is developed to solve the problem. The efficiency of the algorithm is proved by simulated data from a real cold rolling production system.
cooling time raw materials requirement algorithm lot-sizing planning cold rolling
Wenpeng Wang Tieke Li Xinning Yu
Qingdao University of Science and Technology, Qingdao 266061, China University of Science and Technology Beijing, Beijing 100083, China
国际会议
The Tneth International Conference on Industrial Management(第十届工业管理国际会议 ICIM 2010)
北京
英文
325-327
2010-09-16(万方平台首次上网日期,不代表论文的发表时间)