会议专题

In-situ stress measurement and rockburst possibility in deep tunnel at a hydro-power station

To study the relation between stress and rockburst during tunnel excavation at a hydro-power station, in-situ stress measurements are carried out by hydraulic fracturing method. the maximum compression stress and minimum compression stress within the tunnel cross—section are obtained by stress analysis. The possibility of rockburst is analyzed with rockburst criterion, and provided the scientific basis and technological support for the design and construction of the tunnel engineering.

L. Bao S. Zhao

Institute of Crustal Dynamics, China Earthquake Administration, Beijing, China

国际会议

The Fifth International Symposium on In-situ Rock Stress(第五届国际岩石应力研讨会)

北京

英文

351-353

2010-08-25(万方平台首次上网日期,不代表论文的发表时间)