This paper first introduces the Direct method and discusses the PEBS’s shortcoming.A new method is advanced about solving the critical clearing time of three-phase short fault and is proved by an example. The result proves the feasibility of the method. As a discussion, the method about on-line solving the CCT of three-phase short fault has a certain practical meanings.
CCT three-phase short circuit fault branch potential energy improved PEBS
YAN Chang-you ZHOU Xiao-xin Qiu Weijiang Chen xujiang
China Electric Power Research Institute, HaiDian District 100192, Beijng City, China
国际会议
The International Conference on Electrical Engineering 2009(2009 电机工程国际会议)
沈阳
英文
1-7
2009-07-05(万方平台首次上网日期,不代表论文的发表时间)