Construction of the Nam Ngum 2 CFRD
The Nam Ngum 2 Hydroelectric Power Project (NN2 HPP) located approximately 90 km.north of Vientiane,Lao PDR. The dam is concrete face rockfill dam (CFRD) with height of 182 m. The Construction schedule of the project was limited concession period. The Engineering and Construction are very challenge to complete the project in time. The performance of rockfill and face slab is importance for CFRD,which can ensure by strictly control the quality of rockfill.
NN2 HPP CFRD dam
Weerayot Chalermnon Apichat Sramoon Rawee Sittipod
CH Karnchang (Lao) Company Limited,Lao PDR TEAM consulting Engineering and Management Co.,Ltd Nam Ngum 2 Power Company Limited
国际会议
The 1st International Symposium on Rockfill Dams(第一届堆石坝国际研讨会)
成都
英文
511-516
2009-10-18(万方平台首次上网日期,不代表论文的发表时间)