Investigation of 2008’ Frozen Disaster and research on De-icing in Guangdong Power Grid
In early 2008 in Guangdong Province in northern Guangdong power grid suffered a serious frozen disaster. The disaster situations of northern Guangdong power grid such as collapse of towers, breakage of lines and damages of transforming equipments are discussed, and the causes and lessons from the frozen disaster damage are summarized. The analysis on the frozen disaster of North Guangdong power grid shows routing selection and improved permission design limit on the new and rebuilding lines should be focused. And effective anti-ice and removing-ice methods should be studied.
Guangdong power Grid Frozen Disasters Lines Icing Icing Areas
Ping-yuan Liu Hong-ming he chun-ping pan
Guangdong Power Grid Corporation Electric Power Research Institute,Guangzhou China 510600 Guangdong Electric Designment and Research Institute,Guangzhou China 510600
国际会议
2008 China International Conference on Electricity Distribution (CICED 2008)(2008中国国际供电会议)
广州
英文
1-5
2008-12-10(万方平台首次上网日期,不代表论文的发表时间)