The Research on Conformance Testing Platform of Numerical Substation

Communication in numerical substation is very complicated. It is necessary to perform the conformance testing for devices in numerical substation. Three types of conformance testing are provided in this paper. 1)system performance oriented testing, 2)function oriented testing, 3)communication services oriented testing. The relationships among the three types of testing are analyzed. Three types of conformance testing guarantee three type of interoperation of devices in numerical substation. The interoperation based on communication services is the base of the interoperation based function. The function oriented conformance testing has closer relationship with the real project. IEC61850-10 was specified for the conformance testing of communication services. Its limitation is analyzed. The requirements of function oriented testing for the devices on station level, bay level and process level in numerical substation are studied. The idea on how to set up a conformance testing platform for numerical substation is introduced. The concrete function oriented testing platform is provided. The application and effect of the testing platform are given.

Numerical Substation IEC61850 Interoperation Conformance Testing Platform

JIONGCONG CHEN YANMING REN XINHUA GAO YANGJUN JIN

Guangdong Power Test & Research Institute,Guangzhou 510600,China Beijing Sifang Automation CO.,LTD,Beijing 100085,China

国际会议

2008 China International Conference on Electricity Distribution (CICED 2008)(2008中国国际供电会议)

广州

英文

1-5

2008-12-10(万方平台首次上网日期,不代表论文的发表时间)