Beam dynamics studies on BEPC-Ⅱ storage rings at the commissioning stage

During the 1st and 2nd stages of the commissioning of the upgrade project of the Beijing Electron Positron Collider (BEPC II), which started on Nov. 12, 2006 and Oct. 24, 2007, respectively, we got the luminosity one tenth of its design value, provided beams to synchrotron radiation users for about 4 months, and studied beam dynamics as well. In this paper, some beam dynamics studies on the storage rings and their preliminary results are given.

BEPC Ⅱ commissioning beam dynamics luminosity

QIN Qing WANG Jiu-Qing WEI Yuan-Yuan WEN Xue-Mei XING Jun XU Gang YU Cheng-Hui ZHANG Chuang ZHANG Yuan ZHAO Zheng ZHOU De-Min HUANG Nan LIU Wei-Bin LIU Yu-Dong PENG Yue-Mei QIU Jing WANG Dou WANG Xin-Hao WANG Na