State of Art of Compacted Concrete Face Rockfill Dams
1 IntroductionThe development of concrete face rockfill dams is well commented in the technical literature.Cooke. Initially dumped rockfill was used with problems of leakage and deformation of therockfill which caused excessive stresses in the concrete face slab and rupture of the compressionjoints. The transition to compacted rockfill occurred during early 60s when in Europe was developedthe vibratory compactor roller. Some concrete and asphalt face dams were built with compactedrockfill and excellent performance.
B.Materón
Bayardo Materón & Associates,Brazil
国际会议
2007年中国高坝关键技术交流会(Workshop on High Dam Know-How 2007 China)
宜昌
英文
1-9
2007-05-22(万方平台首次上网日期,不代表论文的发表时间)