The Treatment on the Upstream Surface Cracks of the RCC Cofferdam of Phase III of TGP
The cracks on the upstream surface of the RCC Cofferdam of Phase III of TGP were treated with the method “plugging in the front and draining on the back, which proved effective and can be taken as reference of other projects. The paper introduces the method in detail.
RCC cofferdam surface crack treatment TGP
Zou Jianping Shi Huiliang
Dam & Powerhouse Supervision Department of Three Gorges Project Economic & Technical Development Cor Dam & Powerhouse Supervision Department ofThree Gorges Project Economic & Technical Development Corp
国际会议
西安
英文
1-12