会议专题

Stability Analysis on Final Pit Slope of Surface Mine Based Finite Difference Method

With the open pit mine being continuous explored and slope becoming steep, slope stability problem becomes more important. Thus keeping slope stable has very significant meaning. Then Bang Moshan Iron Mine is taken for an example to assess slope stability. By application of finite difference code Fast Lagrangian Analysis of Continua(FLAC) and its arithmetic process, the analysis on rock slope stability of Bang Moshan lrion Mine was carried on based on the calculation of stress and strain, element displacement vectors, plastic state of slope, hydrolytic weakening properties and then the safety factors were carried out. The quantitative analysis of final slope stability for open pit mine was coneluded, and basic analysis for failure prediction and control on final pit slope was provided.

open pit mine finite difference method slope stability failure prediction

ZHU Ming YAO Xulong YUE Xin LIU Lifeng ZHU Kaiyu PENG Jihuan

College of Resource and Environment,Hebei Polytechnic University,Tangshan 063009,Hebei,China Bang Moshan Iron Mine,Tangshan Steel and Iron Group,Tangshan 064409,Hebei,China

国际会议

The 2008 International Symposium on Safety Science and Technology(2008年安全科学技术国际会议)

北京

英文

2180-2183

2008-09-24(万方平台首次上网日期,不代表论文的发表时间)