SEISMIC DESIGN OF THE CUT AND COVER TUNNEL OF THE CANADA LINE RAPID TRANSIT

Construction of the Canada Line Rapid Transit Project is currently underway in Vancouver, BC. The 19 km rapid transit system includes 6.6 km of cut and cover box structure one of the longest cut and cover rapid transit tunnels in Canada. The design for the cast-in-place reinforced concrete box included standard side-by-side, stacked, special cross-over single box and transitional rollover configurations. The seismic design accounted for both pressure-based and racking displacement-based demands. The racking displacements were based on state-of-the-art research on soil-structure interaction analyses. Four different types of soil conditions were encountered over the 6.6 km length of tunnel. State-of-the-practice seismic design was utilized to produce cost-effective structures for the project.

Seismic Analysis Cut and Cover Tunnel Racking Displacement Seismic Design Canada Line Rapid Transit

Yuming DING Sean XIAO Samson CHAN Roger WOODHEAD

Senior Structural Engineer, SNC LAVALIN INC., Vancouver, BC, CANADA Structural Engineer, SNC LAVALIN INC., Vancouver, BC, CANADA Manager of Structural Engineering, SNC LAVALIN INC., Vancouver, BC, CANADA Technical Director, Canada Line Project, and President, WOODHEAD CONSULTANTS INC,North Vancouver, BC

国际会议

14th World Conference on Earthquake Engineering(第十四届国际地震工程会议)

北京

英文

2008-10-12(万方平台首次上网日期,不代表论文的发表时间)