Construction of Full Section Roller Compacted Concrete Gravity Dam on Guizhou Suofengying Hydropower Project

Suofengying hydropower station is located on the Liuguang reach of Wujiang River, the boundary of Xiuwen County and Qianxi County of Guizhou province, China. It is the third cascade power plant following the Hongjiadu hydropower station on Mainstream of Wujiang River. The dam is a full section RCC dam with a maximum height of 115. 8m. According to Suofengying project features, advanced technology of domestic RCC construction has been completely applied. Scientific and rational construction technical measures have been worked out, and concrete warehousing, temperature control, mixing MgO in full section and other aspects have been developed. It is a bold attempt to bury PVC pipe with cool water to reduce inside and outside temperature difference of concrete for summer RCC construction. This paper introduces construction technology of Suofengying full section roller compacted concrete dam in detail.

suofengying Hydropower Station dam RCC construction measures

Zheng Zhiren

Chinese Eighth Water Conservancy and Hydropower Engineering Bureau, No. 2 Chengnan Zhong road. Changsha 410007, China

国际会议

第五届碾压混凝土坝国际研讨会(The Fifth International Symposium on Roller Compacted Concrete(RCC))

贵阳

英文

691-698

2007-11-02(万方平台首次上网日期,不代表论文的发表时间)