Design and Rapid Construction of Phase III RCC Cofferdam of the Three Gorges Project

The Phase III RCC cofferdam of the Three Gorges Project (TGP), with a max height of 115m, is a Class I temporary structure. On the first stage (phase I), the right shoulder of cofferdam under EL. 50m (58m) was constructed. On the second stage, RCC volume placeed was about 1. 1 million m3, which was finished within 4 months, with a max monthly placement intensity of 476, 000m3. The paper is mainly focused on the structural layout design of RCC cofferdam, rapid RCC placement schemes and measures.

Three Gorges Project cofferdam design rapid placement