Optimal Scheduling of Sequential Multipurpose Batch Plants under Unexpected Events
As the successor work for proposing a modified MILP model for scheduling of sequential multipurpose batch plants1, this paper presents new optimal strategies for the scheduling of sequential multipurpose batch plants under several unexpected events. The events include product release dates, rescheduling upon arrival of a new order, and the minimization of total earliness. To find the optimal solutions in complex situations, scheduling problem is formulated to an MILP model. A typical example is tested with the proposed strategies, showing that the schedule of sequential multipurpose batch plants is more flexible in the varying market circumstances.
batch process sequential multipurpose plants scheduling unexpected events
PAN Ming QIAN Yu LI Xiuxi
School of Chemical Engineering,South China University of Technology,Guangzhou,510640,P.R.CHINA