The Practice of Risk Identification and Assessment of Shield Tunnelling in Chengdu Metro
It is the first time that Earth Pressure Balance machine is used to construct metro tunnel in Chengdu. The ground condition is full of water and the content of cobble is very high. The risk mechanism of this project is studied, and the main risks are found out. The main risks are assessed and classified employing the method of P=R×C, then the risk classification is determined. These studies ensure the project advance successfully.
S.H.Zhou T.T.Song
Key Laboratory of Road and Traffic Engineering of the Ministry of Education, Tongji University, Shanghai, China
国际会议
上海
英文
2007-10-18(万方平台首次上网日期,不代表论文的发表时间)