会议专题

Case Study of AC Interference on 20 km Buried Pipeline:Field Test and Mitigation Design

  AC interference on pipelines caused by nearby HVAC power lines can lead to electric shock hazard and AC corrosion.It threatens the safety of pipe operators as well as pipelines.The pipeline from Jiaozhou to Jiaoxi is close to many HVAC power lines and suffers serious AC interference (the highest voltage can reach 40 V).A case study has been conducted to design and optimize mitigation measure with the help of computer simulation.In this paper, the methods to test AC voltage in field and to survey relative locations were introduced in detail.And then, computer model was established based on the collected information.In order to make the model meeting field test result, the model was adjusted.The result showed that the final model was well accorded with field test result.3 types of grounding beds were discussed.The mitigation schemes, which can decrease AC interference voltage under 10 V, were got.The results indicated that 650 m Zn ribbons or 6 deep wells or 10 grounding grips can reach the mitigation target

AC interference mitigation design field test computer simulation

Zitao Jiang Yanxia Du Minxu Lu Liang Dong Dezhi Tang

Institute for Advanced Materials and Technology,University of Science and Technology Beijing,30 Xueyuan Rd,Haidian District,Beijing P.R.China 100083

国内会议

2013中国国际管道会议暨第一届中国管道与储罐腐蚀与防护学术交流会

廊坊

英文

348-356

2013-09-01(万方平台首次上网日期,不代表论文的发表时间)